Mapping of resource consumption in transport infrastructure project - A case study of BĂ„rhultsmotet
Paper in proceeding, 2016

The purpose of the study is to 1) investigate the possibility to collect and present data of consumed human resources from all stakeholders over the project life cycle of transport infrastructure project; 2) discuss the use of such information with regard to the evaluation and suggestion for improvement of project performance. A well-defined engineering project, the interchange BĂ„rhultsmotet consisting of two bridges over the route 40, was used as case study. A diagram presenting consumption of human resources over the project life cycle was constructed, starting at the initial project phase in the client organization and ending when the bridge was handed over for operation. The diagram raise a number of questions whether or not the time spent is value adding, especially between project phases considering the long lead times. The diagram also inspires to discussions of topics for further studies, for example the how to manage the gap (e.g. transfer/loss of information) between planning, design and construction phases in order to utilize the human resources more efficiently.

Resource utilization

Construction project

Loss of information

Lead times

Author

T. Olofsson

Luleå University of Technology

Christina Claeson-Jonsson

Chalmers, Civil and Environmental Engineering, Construction Management

Peter Simonsson

Swedish Transport Administration

IABSE Congress Stockholm, 2016: Challenges in Design and Construction of an Innovative and Sustainable Built Environment

Vol. 2016 573-579

19th IABSE Congress Stockholm 2016: Challenges in Design and Construction of an Innovative and Sustainable Built Environment
Stockholm, Sweden,

Driving Forces

Sustainable development

Areas of Advance

Building Futures (2010-2018)

Subject Categories

Construction Management

Environmental Management

More information

Latest update

4/27/2020