Effects on logistics of increased on-site sorting
Other conference contribution, 2020
The construction industry is one of the largest producers of waste and the EU waste framework directive (2008/98/EC) has established a target of 70% of construction and demolition waste (CDW) to be recycled by 2020. However, except for a few EU countries, only about 50% of CDW is recycled
(European Commission, 2018). In order to increase recycling rates, sorting of waste material is of high importance (Kurdve et al., 2019). Still, there are different believes of where the sorting should take place; on-site or upstream the supply chain, e.g. at the waste collection company (CIRF, 2019).
The purpose of this study is to increase the understanding of the effects that an increased on-site sorting may have on logistics, measured in terms of load factors and collection costs.
Research Approach
The study takes a quantitative approach, using empirical data from 22 Swedish construction projects of a construction company during the years 2016-2019. Data was gathered from the databases and bookkeeping of the construction company and the waste collection provider. This was complemented with interviews of personnel knowledgeable of the data from the two companies.
Findings and Originality
No statistic correlation could be found between on-site sorting level and load factor. Thus, an increased sorting level does not per definition add complexity in logistics. The sorting applied in the projects has in total saved about EUR 300 000 for the construction company, compared to not sort
at all. This saving is in terms of lower treatment costs. However, storage and handling costs may increase for higher sorting levels, which is not calculated in this study. The saving in treatment cost also differs between material types, where greatest savings occur for combustible material compared with inert material.
Research Impact
Since 2000, CDW management has been attracting increasing attention from researchers around the world (Kambiz et al., 2016). Earlier studies in CDW management reports on pros and cons of on-site sorting (e.g. Tam et al., 2009; Wang et al., 2010). To our knowledge this is the first study that tries to empirically determine the effect of on-site sorting on load factors and collection costs.
Practical Impact
The study gives some guidelines in how construction companies could improve sorting rates and at the same time keep collection costs low. For example, our results indicate that it is positive to sort as much as possible of the chosen material from the mixed fractions and carefully choose the fractions to sort.
sorting
Construction waste
collection costs
logistics
Author
Linea Kjellsdotter
The Swedish National Road and Transport Research Institute (VTI)
Logistics & Transportation
Martin Kurdve
Chalmers, Technology Management and Economics, Supply and Operations Management
RISE Research Institutes of Sweden
Mats Johansson
Chalmers, Technology Management and Economics, Supply and Operations Management
Cardiff / Online, United Kingdom,
Subject Categories
Other Mechanical Engineering
Environmental Management
Driving Forces
Sustainable development
Areas of Advance
Transport