Scenario for near-term implementation of partial capture from blast furnace gases in Swedish steel industry
Other conference contribution, 2019
This work discusses the near-term (the 2020s) implementation of partial capture at a Swedish steel mill and the economic viability of such implementation dependent on the energy price, carbon price, and required reductions in CO2 emissions. Based on previous work [9][10,11] on partial capture in steel industry a cost estimation of a capture system for the BFG is conducted including CAPEX and OPEX of the MEA capture unit, gas piping, and recovering heat from the steel mill. The costs are summarized as equivalent annualized capture cost (EAC) and set into relation to transport and storage costs as well as carbon emission costs to form the net abatement cost (NAC) according to Eq. (1)
𝑁𝐴𝐶=𝐸𝐴𝐶+ 𝑡𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡&𝑠𝑡𝑜𝑟𝑎𝑔𝑒 𝑐𝑜𝑠𝑡 −𝑐𝑎𝑟𝑏𝑜𝑛 𝑝𝑟𝑖𝑐𝑒
[€/𝑡𝐶𝑂2]
(1)
Figure 1 shows how EAC for BFG varies with the capture rate and the cost of steam for different heat recovery technologies represented by the steps in the curve ( see explanation in [9]). Note that partial capture from BFG is more economical than the full capture benchmark. The most cost-efficient case of 28 €/t CO2 captured is achieved for BFG capture fueled by steam from back-pressure operation (at the expense of electricity production), flue gas heat recovery and flare gas combustion. The transport and storage cost applied in Eq (1) represent ship transport from the Bothnian Bay to a storage site in the Baltic Sea , according to Kjärstad et el.[12]. Transport and storage cost range within 17 – 27 €/t CO2 depending on scale.
These installation and operation cost for capture, transport and storage are set into relation with various scenarios on future carbon and energy (electricity) prices in Europe and Sweden. For example, Figure 2 illustrates a scenario in line with IEA’s sustainable development scenario to restrict global warming to 2°C. The carbon prices are adapted from WEO 2018 [13] and increase from 20 € to 120 € per tonne CO2 by 2040 and the electricity prices of 42-52 €/MWh (increasing with time) are based on latest results from the NEPP project [14]. In this scenario, partial capture from BFG could become economic viable in 2029, construction in 2020 with operation from 2022/23 onwards is likely to pay off within a lifetime of 20 years only. This work demonstrates the viability of partial capture as cost-efficient mitigation measure for the steel industry and illustrates conditions for an early implementation in the 2020s.
This work is part of the CO2stCap project (Cutting Cost of CO2 Capture in Process Industry) and
funded by Gassnova (CLIMIT programme), the Swedish Energy Agency, and industry partners.
amine absorption
cost-estimation
partial capture
blast furnace gas
steel industry
MEA
Author
Max Biermann
Energy Technology 3
Fredrik Normann
Chalmers, Space, Earth and Environment, Energy Technology
Filip Johnsson
Chalmers, Space, Earth and Environment, Energy Technology
Mikael Larsson
Swerim AB
David Bellqvist
SSAB AB
Ragnhild Skagestad
SINTEF
Hassan Ali
University of South-Eastern Norway (USN)
Trondheim, Norway,
Cutting Cost of CO2 Capture in Process Industry
Swedish Energy Agency (P40445-1), 2015-07-01 -- 2019-08-30.
Subject Categories
Energy Engineering
Other Environmental Engineering
Energy Systems
Areas of Advance
Energy