Drip sealing of tunnels in hard rock: A new concept for the design and evaluation of permeation grouting
Artikel i vetenskaplig tidskrift, 2010

This paper presents a new pre-excavation grouting concept to prevent dripping and reduce the inflow into a railway tunnel. For this purpose, the tunnel's roof was drip-sealed using colloidal silica and the walls and invert of the tunnel were grouted with cement. The grouting design process followed a structured approach with pre-investigations of core-drilled boreholes providing parameters for the layout. Water pressure tests and pressure volume time recordings were used for the evaluation. Results showed that the design was successful: the total transmissivity was reduced from 4.9 x 10(-08) m(2)/s to the measurement limit (1.6 x 10(-08) m(2)/s), and the dripping was reduced to eight spots from the roof. Improved rock characterisation showed that the grout hole separation was within the transmissivity correlation length and that grouting efficiency depends to a large extent on the dimensionality of the flow system of the rock mass. (c) 2009 Elsevier Ltd. All rights reserved.

Grouting design

Dripping

Grouting evaluation

Silica Sol

Hard rock

Cement

Författare

Christian Butron

Chalmers, Bygg- och miljöteknik, Geologi och geoteknik

Gunnar Gustafson

Chalmers, Bygg- och miljöteknik, Geologi och geoteknik

Åsa Fransson

Chalmers, Bygg- och miljöteknik, Geologi och geoteknik

Johan Funehag

Chalmers, Bygg- och miljöteknik, Geologi och geoteknik

Tunnelling and Underground Space Technology

0886-7798 (ISSN)

Vol. 25 2 114-121

Ämneskategorier

Samhällsbyggnadsteknik

DOI

10.1016/j.tust.2009.09.008

Mer information

Skapat

2017-10-08