Optimal time for contractors to enter infrastructure projects
Paper i proceeding, 2021
done by procuring the contractor during the design phase of a project. There are different approaches to which time the contractor
is introduced. This research paper aims to investigate the optimal time for contractors to enter infrastructure projects. In order to
do this, an empirical study was conducted, where interviews were held with nine representatives from an ongoing ECI project in
Sweden. The studied project was procured by the Swedish Transport Administration, and the contractor entered the project at the
beginning of the design phase, before a land acquisition plan had been developed. This is the first time in Sweden that a contractor
has been procured this early in a road project. The findings from the interviews show that responsibility, understanding, innovation,
risk management, relationship-building and implementation are the aspects that have been affected due to ECI. By analyzing and
discussing the results, it was concluded that involving the contractor as early as in the studied case has been beneficial, and that
involving the contractor as early as possible in infrastructure project is favorable.
timing
collaborative management method
ECI
Författare
Freddy Antonsson
Student vid Chalmers
David Lindvall
Student vid Chalmers
Johan Lagerkvist
Chalmers, Arkitektur och samhällsbyggnadsteknik, Konstruktionsteknik
Rasmus Rempling
Chalmers, Arkitektur och samhällsbyggnadsteknik, Konstruktionsteknik
Procedia Computer Science
18770509 (eISSN)
Vol. 196 990-998Braga, Portugal,
Industriell konstruktion, upphandling och produktion av byggnadsverk och andra tekniska detaljer
Trafikverket (2020/65121), 2020-08-01 -- 2025-12-31.