The CO2 avoidance cost of a large scale O2/CO2 power plant
Paper i proceeding, 2005

This work evaluates the fixed and running costs together with the CO2 avoidance cost of an O2/CO2 combustion process. The work is based on a comprehensive process study applied to commercial process data from an 865 MWe lignite fired reference power plant and large scale air separation units (ASU), in combination, with a detailed design study of the flue gas treatment and CO2 compression train (FGTCC) [1]. All costs for the process layout proposed in [1] are gathered from industry. Although an existing reference power plant forms the basis of the work, the study is directed towards a new state-of-the-art lignite-fired O2/CO2 power plant.

Författare

Klas Andersson

Chalmers, Energi och miljö, Energiteknik

Bastian Nelsen

Chalmers, Energi och miljö

Filip Johnsson

Chalmers, Energi och miljö, Energiteknik

Lars Strömberg

Chalmers, Energi och miljö

Proceedings of the 7th International Conference on Greenhouse Gas Control Technologies 5– September 2004, Vancouver, Canada

1787-1790

Ämneskategorier

Annan naturresursteknik

Mer information

Skapat

2017-10-07